When I create multiple programs in the program configuration with the D300win, will these programs be executed in the order shown in the program configuration?

When I create multiple programs in the program configuration with the D300win, will these programs be executed in the order shown in the program configuration?
Category : 

Answer

No, they won't. The programs will be executed from top to bottom for each task to which they are assigned, 'DEFAULT,' 'FIXED_CYCLE' and 'EVENT' respectively.